CASE STUDY
Revenue Generation of ~$4 MN over three months Enabled Under Severe Time Constraints
Background
Industry Segment
Oil & Gas
Arm Solution
Maintainance Services-Major Overhaul
Equipment
Caterpillar make diesel engines
CHALLENGE
- Rig owner had only 45 days in hand to complete Major Overhaul on four nos. of CAT 35 series engines.
- Rig was located at Dubai Dry dock and the above timeline included supply of required spares
- If the deadline was missed, there could have been a delay of over 90 days. This could have been a huge opportunity loss for the rig owner.
- Due to space constraint inside engine room, at a time not more than two engines could be worked upon
- In a similar situation previously, the rig owner had suffered 90 days deputation delay due to the inability of the local service provider to finish the job on time.
SOLUTION
- Neptunus has been a preferred partner to this customer in India. The customer trusted Neptunus to handle this challenging assignment in the UAE.
- Neptunus’ project management team ensured mobilization of two service teams and delivery of required spares at site on time.
- The teams overcame some teething problems pertaining to cramped space and labour shortage to manage movement of critical components like the crankshaft, old power packs, alternators & other old spares.
- With the teams working almost 17 hours a day & with strong project management overhauling was completed on the 40th day. It took two more days to complete load trials & hand over the engines to the customer.
BENEFITS
- Rig owner deputed the rig on time and this enabled revenue of 90 days * $45,000 = $4mn
- For the rig owner, the cost of engine overhauling by Neptunus was lesser than the local service provider.
- The rig owner could also protect his reputation by delivering on the commitment to the charterer.