Home » Blog » Maintenance & Reliability » Marine Engine Major Overhaul Schedule for Offshore 4-Stroke Main Engines
| System / Component | Scope of Work |
|---|---|
| Engine Performance | Record engine performance before overhaul and record crankshaft deflection. |
| Filters | Inspection and cleaning of filters. Overhaul self-cleaning filter, especially the self-cleaning device (if equipped). |
| Lube Oil System | Lube oil replacement and sump cleaning. |
| Engine Foundation | Check tightening of engine fixing bolts. |
| Starting Air Distributor | Replace gasket. |
| Starting Air Valve | Overhaul starting air valve. |
| Piston | Replace pistons. Measure diameter of piston pin. Replace piston rings. |
| Turbocharger | Overhaul turbocharger, measure clearances, and replace bearings. |
| Air Cooler | Clean air side and cooling water side. |
| Lube Oil & Fuel Oil Filters | Inspection and servicing as required. |
| Cooling Water Pump | Replace mechanical seal and oil seal. Replace ball bearings. Check pinion. |
| Cooling Water & Lube Oil Coolers | Overhaul and clean inside of tubes. Replace zincs, O-rings, and gaskets. Pressure test coolers. |
| Fuel Injection Union | Check seat and inner surface. Replace O-rings. |
| Crankshaft | Measure crankshaft deflection. Conduct visual inspection of crank journals. Measure crank pin diameter. Replace main bearings and thrust bearings. |
| Camshaft | Carry out visual inspection of camshaft and take readings. |
| Crankcase | Check for water condensation and corrosion. Inspect inside and outside condition of crankcase and paint condition. |
| Gear Train | Inspect timing gears. Overhaul all gears. Conduct dye penetration testing on gear cranks. Inspect and replace bearings. |
| Connecting Rod | Calibrate piston pin bush and replace if required. Replace crank pin bolts and connecting rod bearings. Check and record connecting rod ovality. |
| Cylinder Liner | Remove and clean cylinder liner. Clean and replace O-rings. Conduct dye penetration test on upper flange for cracks. |
| Cylinder Head | Replace rocker arm bushings. Replace valve springs. Replace cotters, intake and exhaust valve guides. Replace valve rotators. Measure rocker arm shaft clearance. Conduct hydro pressure test and dye penetration test on cylinder head face. |
| Exhaust Manifold Threads | Clean all threads and replace bolts where required. Replace all gaskets and O-rings. |
| Valve Gear | Overhaul tappets and shafts. |
| Fuel Injection Pump | Overhaul fuel injection pump. Inspect plunger and barrel and replace as required. |
| Governor Driving Device | Check gears and measure backlash. Replace oil seals and ball bearings. |
| Fuel Feed Pump | Replace coupling, oil seals, gaskets, and ball bearings. |
| Lubricating Oil Pump | Replace bushings and O-rings. |
| Exhaust Manifold | Inspect expansion joints for leakage. |
| Fuel Injector | Replace fuel injection nozzle, spring, push rod, and pin. Conduct injection pressure test and spray pattern check. Replace gasket and O-rings. |
| Main Layshaft / Governor Layshaft | Inspect layshaft. Replace bearings and bushings. |
| Safety Checks & Sea Trial | Check engine safeties under supervision. Set tappets and conduct engine sea trial. |
| External Service | Scope |
|---|---|
| Turbocharger Overhaul | Complete turbocharger overhaul. |
| Cooler Cleaning | Cleaning of all coolers and associated cooling equipment. |
| Governor Overhaul | Complete governor overhaul. |
| Liner Honing | Cylinder liner honing. |
Leave a Reply
Latest Posts
30 Years of Neptunus – A Legacy of Excellence
Complete 30K Overhaul of EMD 12-645-E8 Main Engine on Jack-Up Drilling Rig in Egypt
Complete 24K Overhaul of Niigata 8L28HX Main Engine on Offshore Supply Vessel in Ghana